Otter Creek Communications Union District
Removing Barriers to Fast, Reliable Internet
Connecting the People of Vermont
Otter Creek Communication Union District’s mission is to bring affordable reliable high-speed broadband service to the residents, businesses and municipalities of our member towns:
Benson
Brandon
Castleton
Chittenden
Fair Haven
Goshen
Hubbardton
Mendon
Pawlet
Pittsford
Poultney
Rutland City
Rutland Town
Shrewsbury
Sudbury
Wells
West Haven
West Rutland
Is Your Address Eligible for Fiber?
Fidium Fiber
Compare the colored areas of the map to the key below to determine when construction is scheduled for your area.
Map Area | Construction Starts | Service Available |
---|---|---|
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
■ | early-mid July 2024 | Completed |
GoNetSpeed
Compare the colored areas of the map to the key below to determine when construction is scheduled for your area.
Map Area | Construction Starts | Service Available |
---|---|---|
■ | July 2024 | Oct 2024 |
■ | June 2024 | Nov 2024 |
■ | June 2024 | Complete |
■ | Aug 2024 | Nov 2024 |
■ | Complete | Complete |
■ | Sept 2024 | Q1 2025 |
■ | June 2024 | Oct 2024 |
■ | Complete | Complete |
■ | June 2024 | Nov 2024 |
■ | Complete | Complete |
■ | Aug 2024 | Dec 2024 |
■ | Sept 2024 | Nov 2024 |
* Pending Green Mountain Power Pole Placements